Project Management & Contract Administration - External Repair & Redecoration Works
Instruction:
APA were appointed as Project Managers and Contract Administrators for the refurbishment of the East Gable façade serving the historic Olympia Grand. The works included the stripping off of the existing flashing details, glazing replacement, and waterproofing of the façade using the a cold applied system and glazing products, along with redecoration of the main barrel arch.
The works also included the design and erection of a large extensive scaffold and internal crash deck which was required to be co-ordinated within the client’s extremely tight timescales to coincide with the exhibitions held in the Olympia Grand. Working alongside the appointed Quantity Surveyors Mooney Kelly Ltd. the works were successfully completed in 2014 without any impact upon the exhibitions.
Contract Value:
£300,000+VAT.