Greenwich Millennium Village, London

Role:     

External Repair and Redecoration - Phase 1

Instruction:

APA were appointed in 2017 as Contract Administrators for Phase 1 of the proposed external repair and redecoration works of 6 separate blocks, containing circa 150 flats, built circa 2000.  The works were split between two different contractors and included the full repair and redecoration of the building fabric including timber repairs to the windows repair, redecoration the timber weatherboarding and cleaning of the render facade.  Following successful completion of this phase, APA have been instructed to undertake Phase 2 of the works which are due to commence in Summer 2019.

Contract Value:

Phase 1 of the project was completed in December 2018 with an agreed final figure of circa £1,200,000.00+VAT.